CEMCAP

Project contents


The CEMCAP project consists of twelve work packages (WP) that are grouped in four sub-projects (SP):

The overall methodology of CEMCAP is to iterate between experimental work in pilot-scale test rigs and simulations of capture technology integration and cost analysis, to assess the impact of CO2 capture on the cement production process.

Technology development and demonstrations in simulated industrial environments (gas compositions and other conditions adapted to replicate the operating conditions of a cement plant) will be conducted during 36 months in SP3 and SP4 (until April 2018).

In order to provide sufficient time for analysis and dissemination of results after the experimental work is concluded, SP1 and SP2 will continue until month 42 (October 2018).