Progress status March 2010: This work package was completed in September 2009. MARINTEK prepare a project internal Technology Road Map report. This report includes 4 possible development scenarios and a list of 18 critical system requirements for a new generation of Arctic construction and intervention vessel
Objective: Prepare road map and project plan
Content: Project partners will work out the revised project plan based on approved project budget and new information that has been received since preparation of project application in February 2008.