Project Organisation

Organization

The INSTALLER project is organized based on experiences from a previous successful project. The project owner on behalf of the consortium is NOV, and SINTEF Ocean holds the role as project leader - also responsible for the administrative management. The Steering Committee is constituted by one person from each partner.

Main activities

The main activities in the project are:

  • H1: Project administration
  • H2: Design basis
  • H3: Installation concept
  • H4: Vessel design
  • H5: Logistics system
  • H6: Concept validation and demonstrator
  • H7: Dissemination and knowledge management

Partners

  • National Oilwell Varco (NOV) - project owner
  • Ulstein
  • Fred. Olsen Windcarrier
  • Statoil
  • SINTEF Ocean - project leader