Project Organisation
Organization
The INSTALLER project is organized based on experiences from a previous successful project. The project owner on behalf of the consortium is NOV, and SINTEF Ocean holds the role as project leader - also responsible for the administrative management. The Steering Committee is constituted by one person from each partner.
Main activities
The main activities in the project are:
- H1: Project administration
- H2: Design basis
- H3: Installation concept
- H4: Vessel design
- H5: Logistics system
- H6: Concept validation and demonstrator
- H7: Dissemination and knowledge management
Partners
- National Oilwell Varco (NOV) - project owner
- Ulstein
- Fred. Olsen Windcarrier
- Statoil
- SINTEF Ocean - project leader